For Immediate Release
Completion Ceremony Of Carigali Hess Project
Bangkok, 19 September 2007 - The “Carigali
Hess Bumi, Bulan and Suriya Gas field Development”
project in Malaysia-Thailand Joint Development area by
CUEL Limited, a Thailand-based offshore construction company,
has finally been completed after 16 months of unremitting
work. The CKR-3 Gas Compression Module is scheduled to
sail away on the 22 September 2007, after the BMA, SYA
and BLA Jackets that already sailed away on the 2 June,
12 July and 8 August 2007 respectively.
The completion ceremony was held on the 4 September
2007 at CUEL yard. Mr. Tan Sri Abu Talib Othman, Co-Chairman
of MTJA presided over the event. The completion ceremony
was a good indicator of CUEL’s staff cohesiveness,
which will eventually lead us one step closer to our
commitment “Toward higher achievement in excellence.”
|